Plan Swiftly Logo
How It Works Pricing Get Started

Event Tree

The Event Tree shows what could happen to your project. It starts from the project's Current state, follows the milestones you intend to reach, and branches off to the outcomes you'd rather avoid, or that are simply different. Each branch is an event, and your activities can make an event more or less likely. Use it to see where the plan could go wrong and what you're doing about it.

The Event Tree is on the Overview tab, after Lifecycle. It's available on plans that include all tabs.

Outcomes

An outcome is a state the project can reach. There are four kinds:

Kind What it is
Current state Where the project is now, as you understand it. Every project has one, and the tree starts here.
Milestone A point you intend to reach, the same milestones you manage on the Lifecycle tab. Gates are shown as such.
Neutral An outcome that isn't the plan but isn't a problem either, such as a change of scope.
Undesirable An outcome you want to avoid, such as a licence delay or a safety incident.

Like a milestone, any outcome can have criteria that say what's true when it's reached, and can be marked reached. Describe the Current state with criteria too, for example the documents that already exist.

Events

An event takes the project from one outcome to another: "Regulator rejects the safety case" leads from a milestone to "Licence delayed". Each event can have a Likelihood of Low, Medium or High. An event has happened once the outcome it leads to is reached. The events on the milestone path are called As planned: where they lead says what they are.

Reading the tree

  • The Current state and the milestone path run along one row, left to right. Other outcomes branch above and below it.
  • Outcomes are styled by kind. Choose Key at the top right of the tree to see what each style means. A milestone shows Reached and its achievement once recorded.
  • A thicker line is a more likely event; a dashed line has no likelihood set. A line in full colour has happened.
  • The chip on a line counts the activities that diminish (↓) or enhance (↑) the event. It's bold when any influence is strong.

Select an outcome to open its details, with what it connects to highlighted. The details open beside the tree, which stays in view: select another outcome or event to switch to it, or the background (or press Escape) to close them. In the list view and on a phone they open over the page instead. Select an event's line, its name or its chip to open the event. A long tree opens at its start: scroll or drag to follow the path, or use the zoom controls. Full screen gives the tree the whole window.

On a phone, or with the list button, the tree shows as a list: events grouped by the outcome they lead from, then any outcome no event reaches yet.

Building the tree

Choose Edit, then:

  • Draw milestone path links the Current state to each milestone in phase order. It skips links that already exist, so you can run it again after adding milestones. Milestones with no phase are left for you to connect.
  • Add event adds something that could happen. Pick where it starts (From), name it, set its likelihood, and choose where it Leads to: an existing outcome, or New outcome… to create one there and then, with its name and kind. Select an outcome first, or use Add event in its details, and the event starts from it, leading to a new outcome.
  • Add outcome opens the same form for a new outcome first. Choose No event yet under From to add it without an event.
  • Drag from the right edge of one outcome to another to add an event between them.

In an outcome's details, Leads to and Comes from list its events. In an event's details you can set its likelihood and description, and add the activities that influence it. Select an activity to open and edit it.

Deleting an outcome also deletes its events. You can't delete an outcome while another outcome's criteria expect it reached or avoided: its details name those outcomes, so remove the criteria first. Neutral and undesirable outcomes show Not reached until you mark them reached, and only milestones have an acronym, since only they appear on the timeline and Roadmap.

Activities record their influences too. See Activities.

Right-click menus

Right-click an outcome, an event (its line, name or chip) or the empty tree for quick actions. In the list view, right-click a row, or press and hold on a phone.

On Menu
An outcome Jump to Lifecycle and, for a gate, Jump to Organisation. Add event from here… and Add event leading here…. On the graph, Show path from Current state highlights every chain of events that reaches it; choose Clear path, or select the background, to undo it. Mark reached or Mark not reached, Kind, Edit and Delete.
An event Likelihood, Add outcome after… (a new outcome where this event leads), Edit and Delete.
The empty tree Add outcome…, Add event…, Draw milestone path and Fit view.

Anyone who can see the tree gets the jumps, Show path and Fit view (Show path on the graph only). The other items need edit rights and a larger screen. Delete is greyed out while another outcome's criteria expect the outcome, and says which.

Checks and exports

Once your tree has an event, the Health Check looks for likely risks nothing diminishes, undesirable outcomes reached, milestones and outcomes the tree doesn't reach, and loops. The Management Plan, PDF Export, Role Pack and Poster include the tree too. See Offline copies.

Criteria on the Current state count towards your plan: if it already has a product, assessed as met, a later milestone expecting that product (no further along, same version) isn't flagged as unplanned. The Roadmap and Health Check show it as already in place.